Working to Repave and Widen the CCT

Here are photos and diagrams supporting the need to repave and widen the CCT.

As a trail user, you’ve probably noticed that the Capital Crescent Trail (CCT) between Bethesda and Georgetown is overdue for repaving. In fact, the trail was originally paved over 25 years ago (between 1992 and 1996). With only spot repaving since then, much of the trail has its original asphalt. As one of the most heavily used trails in metropolitan Washington, DC, our well-loved CCT is showing its age with wear and deterioration that degrades the integrity of the trail and the experience for everyone who uses it.

The Coalition for the Capital Crescent Trail (the Coalition) has long been advocating for repaving in discussions with the National Park Service (NPS), which owns the DC section of the trail (as part of the C&O Canal National Historic park), and with the Montgomery County Parks Department, which manages the Montgomery County section. Both park authorities acknowledge the need for repaving, and note the challenges associated with funding a project of this scale. Along with repaving, the Coalition also strongly recommends widening the trail for safety and ease of use.

Here’s a breakdown and progress report on that recommended work:

September 2022 update - Repaving is coming, but it will take time and attention

At the CCCT 2022 Annual Meeting on 9/19/2022, the presentations by the National Park Service and Montgomery Parks showed that repaving and improving the CCT is in their plans, although it will take 3 or more years to deliver results on the trail.

The National Park Service (NPS) is further ahead in their process, having completed Scoping and now starting on Design in 2023/2024. Construction is estimated for 2025/2026, assuming their funding plans work out. Assuming these are NPS fiscal years, they start on October 1 of the previous calendar year, so NPS fiscal 2023 starts on 10/1/2022.

For multiple reasons, including environmental study requirements and constraints in the types of funding available to them, NPS will repave at the current 10 foot width. However, they plan to plan to add 2 foot wide gravel shoulders and a 1 foot wide "recovery area" on each aside, increasing the usable width and capacity of the trail. Here are the "Key project elements" from their presentation:

  • Rehab the 10’ wide asphalt pavement end-to-end (3.7 miles)
  • Reconstruct timber retaining walls, railings, and Manning Steps
  • Repair/paint Arizona Ave. Bridge
  • Re-establish gravel shoulders, drainage channels, and recovery area
  • Replace/Upgrade Existing Signage (including re-ordering mile markers from Georgetown)
  • Mark center and edge lines
  • Install two automated bike-ped counters

Montgomery Parks (Parks) has not yet started their process. They committed to starting on a "Facility Plan" for the Capital Crescent and Metropolitan Branch Trails in their Fiscal Year 2024, that begins July 1, 2023. The Facility Plan process is extensive, will take 2 or more years, and "Results in 30% design with reliable cost estimate". Then design, bidding, and contractor selection must be completed before construction can start.  Given this, starting construction in 2027 would be an optimistic possibility. Note the inclusion of the "Metropolitan Branch Trail" is only the short portion in Montgomery County, and makes sense because once the Purple Line section of the CCT opens in mid 2027, it will continue directly onto the Metropolitan Branch Trail, connecting at the Silver Spring Transit Center.

The Facility Plan process includes a lot of community outreach, so it very important that CCT supporters participate in this as much as they can. In part, whatever generates the loudest input by the most people will tend to have the most community impact on the Facility Plan. Here are the "Facility Plan Components" listed in the Parks presentation:

Outreach

  • Community Meetings
  • Site Walks
  • Coordination with Civic Associations
  • Coordination with the Coalition for the Capital Crescent Trail

Trail Planning

  • Master Plan Recommendations
  • Implementation Priorities

Existing Conditions Analysis

  • Trail Survey
  • Signage Inventory
  • Trail and Pavement Conditions
  • Existing Areas of Disturbance
  • ADA Accessibility
  • Natural Resources Inventory
  • Archaeological / Cultural Inventory

Trail conditions

The DC section of CCT is clearly showing wear and age, with a lot of bumps from roots and frost heaves, and many dips due to subsidence, making for a rough surface and increasing the risk of accidents.

While the Montgomery County section is in better shape, it has reached an age where the remaining original asphalt needs replacement to ensure its integrity, and the shoulders need regrading and widening back to 2 feet. There are also several portions that have significant heaving, such as between the Bradley Blvd. overpass and Weiner Plaza south of the Ourisman Plaza.

In addition, although the Montgomery County section has dirt and gravel shoulders over much of its length, the shoulder on one side is missing, rough or narrow at many points. There are also sections with no shoulders, such as just south of the bridge over River Rd, and just south of the bridge that passes over the Dalecarlia Reservoir grounds.

The DC section has no shoulders in most places, and where it does, those shoulders are almost always on just one side of the trail.

Coalition records report that the original cost to pave the Montgomery County section was about $50 per linear foot, while the section in Washington DC was about $25 per linear foot. That cost difference explains why the DC section is in poorer shape—it was paved with a thinner base and asphalt, that is more easily damaged.

Ongoing Advocacy

The Coalition has been trying for years to persuade the NPS and the Montgomery County Parks Department that they need to repave and widen the CCT. NPS manages the section of the CCT in Washington, DC, about 3.7 miles. Montgomery Parks currently manages about 3.36 miles of the CCT running up to downtown Bethesda. Once the Purple Line project completes the CCT from Bethesda to Silver Spring, Montgomery Parks will manage that. In the past, the key limiting factor has always been the issue of funding. However, recent legislation and anticipated major infrastructure appropriations will hopefully address the funding problem.

National Park Service (NPS) The Great American Outdoor Act was enacted in 2020 and under this legislation, the NPS will have access to substantial funding for the upkeep and improvement of its parks and trails.

In addition, the NPS has access to funds under other Federal funding programs. An important program is the Transportation Alternative Program or TA Set-Aside, which is a reimbursable federal aid funding program for transportation-related community projects designed to strengthen the intermodal transportation system. The program aims to expand travel choice, strengthen the local economy, improve the quality of life, and protect the environment by supporting non-traditional projects, such as shard use pathways, linked to the transportation system.

In response to a NPS request, the National Capital Region Transportation Planning Board on July 15, 2021, approved the following grant for work on the CCT:

“Capital Crescent Trail Rehabilitation Phase 1, Planning and Design National Park Service (DC), $449,190

This is the first step in a two-phase project to fully rehabilitate all 3.7 miles of the Capital Crescent Trail in DC. Phase 1 is for design, planning, and environmental compliance. The trail is heavily used and is a segment of the National Capital Trail Network, approved by the TPB in 2020.”

As a result, the NPS can now start the process of addressing the structural and maintenance needs of the CCT. It is a start, but it will take a couple of years for the NPS to develop the plans, complete environmental assessments, invite bids, and then have the actual work done. Consequently, under the best of circumstances, we likely won’t see significant improvements to the surface of the DC section until 2024.

The NPS has been working to resolve some more immediate serious trail problems, such as the recently completed repair work in the Palisades where the slopes both above and below the CCT had eroded due to rainwater runoff and threatened the integrity of the trail.

Montgomery Parks The Coalition has also been in touch with the Montgomery County Parks Department regarding the condition of their section of the CCT. The Parks Department is aware of the need for trail improvements and has said they are working on a plan to accomplish this, including how they intend to fund this project. However, as with the NPS section improvements, it will take years to be achieved.

Widening the trail

Repaving the CCT provides a perfect opportunity to widen it, which the Coalition strongly favors to improve safety and ease of use. A wider trail would also align with best practices for heavily used trails like the CCT, which sees over one million users per year.

The current pavement is 10 feet wide, while current design guidance for a trail as busy as the CCT calls for a minimum of 12 feet paved width with 2 foot unpaved shoulders on both sides.* Note that 12 feet is minimum, not optimum - 14 feet would be better for the peak usage the CCT carries. It would also be particularly helpful to have shoulders on both sides along as much of the trail as possible, to provide adequate space for walkers and runners who choose not to be on the asphalt, and to reduce plant overgrowth onto the pavement that can become difficult to remove, which has been endemic in parts of the DC/NPS section.

In addition, three future trail milestones will increase use and bring users from new areas. First, in the summer of 2021, the Capital Crescent Surface Trail (CCST) will be completed to provide protected bike-only lanes across Wisconsin Ave, connecting the current CCT trailhead at Ourisman Plaza to Elm Street park and to the alternate detour routes to Silver Spring, courtesy of WABA. Second, completion with the Purple Line of a paved, almost completely grade separated CCT from Elm Street park in Bethesda to downtown Silver Spring will bring direct access to Chevy Chase, Lyttonsville, Silver Spring and beyond, increasing both recreational and commuter usage. Third, the later completion of the planned replacement trail tunnel under Wisconsin Avenue will provide safer passage for all, attracting those hesitant to use the CCST to cross Wisconsin Ave. Each of these enhancements will most certainly increase recreational and commuter traffic on the trail.

The CCT between Bethesda and Silver Spring will be "a 12-foot paved trail with 2-foot buffers", when constructed as part of the Purple Line project. This strongly supports widening the rest of the CCT to match.

Arguments for widening the trail

The first 4 points are based on section "5.2.1 Width and Clearance" on page 5-3 of the AASHTO Guide for the Development of Bicycle Facilities, 4th Edition (2012)The Guide's starting statement on width is: "The minimum paved width for a two-directional shared use path is 10 ft (3.0 m). Typically, widths range from 10 to 14 ft (3.0 to 4.3 m), with the wider values applicable to areas with high use and/or a wider variety of user groups."

1) The Guide says "Wider pathways, 11 to 14 ft (3.4 to 4.2 m) are recommended in locations that are anticipated to serve a high percentage of pedestrians (30 percent or more of the total pathway volume) and high user volumes (more than 300 total users in the peak hour)." Pedestrians are at least 30% of users everywhere on the CCT, and are commonly over 50% near the Bethesda trailhead. CCT peak hour user counts are definitely over 300/hour - that is an average of 5 users per minute, which observation will show is exceeded in late afternoon or early evening on many days.

2) The Guide says "Eleven foot (3.4 m) wide pathways are needed to enable a bicyclist to pass another path user going the same direction, at the same time a path user is approaching from the opposite direction." This kind of "passing between" happens regularly on the CCT, regardless of the safety guidance against it. It most commonly involves a bicyclist passing a pedestrian, with a pedestrian or bicyclist on the other side. When there is a pair of pedestrians on one side, which also happen regularly on the CCT, another 2 feet of width is needed for comparable safety, so 13 feet. Passing widths also need to increase when "city bikes" or bikeshare bikes are involved, since those most often have handlebars 25" to 28" wide. The average width of bicycles (handlebars) has increased since the CCT was originally paved.

3) The Guide says "Wider paths are also advisable in the following situations: Where there is significant use by inline skaters, adult tricycles, children, or other users that need more operating width". The CCT definitely has significant use by children, especially on nice weekend days when the trail is busiest. Among "other users that need more operating width", count the increasing numbers of class 2 and 3 electric bikes, electric scooters (both stand-up and the larger sit-on ones), and mopeds (regardless of rules against them.) Some of these powered vehicle users show less caution about passing and pass at higher speeds than than is normal and desirable, treating the CCT more like a commuting route than a shared-use path. Without enforcement, these trail users are there to stay.

4) The Guide says "Wider paths are also advisable in the following situations: Where the path is used by larger maintenance vehicles". Recall the major ruts and muddy messes caused by tree removal trucks on the NPS CCT section during 2020. On a 12 foot wide paved trail, their tires could have stayed entirely on the pavement. Given the large numbers of trees along the CCT and the number of trees that fall across the trail, occasional visits by tree removal trucks will be required to try to stay ahead of the decaying tree problem.

5) Personal observation shows that a somewhat common occurrence on the CCT is pairs of bicyclists riding side by side. When both of those riders are on "city bikes" or bikeshare bikes, their total riding width (with needed clearance between them) is often 5 feet or more, which can leave no clearance to the trail centerline. A wider trail would accommodate this more safely.

6) As noted above: The CCT between Bethesda and Silver Spring will be "a 12-foot paved trail with 2-foot buffers", when constructed as part of the Purple Line project. This strongly supports widening the rest of the CCT to match.

*References for shared-use path design:

Next steps

The Coalition will continue to advocate for trail repaving and widening, and provide updates here on the plans and progress made by the National Park Service and Montgomery County Parks Department for these and other improvements to the CCT.


Showing 1 reaction